**Note: this blog post does not go over the super powerful CMHC MLI Select but the information provides fundamental insights on how construction financing typically works. The CMHC MLI Select product uses similar topics but the cash requirements and loan to values are completely different**
There are 3 BIG things that do not happen, that surprises almost every client I talk to about construction financing.
Land financing is the initial draw for most builders.
If you already own the land outright, you may or may not need this.
The land draw typically ranges from 50-65% but can potentially go higher with some lender products.
The lower range loan to value is typical when the land is not serviced. Since servicing and rezoning can take quite a bit of time, this is one of the big risks when taking on a construction project as the land (especially raw un-serviced land) rates can be quite steep.
As you navigate through the draw term of your mortgage, the funds will be advanced in stages, based on the progress of your project. Generally, you can expect about 4 or 5 draws which are decided at the outset and NOT negotiable once set in stone. The amounts dispensed at each stage adhere to a formula calculated on the percentage of project completion.
How the Draw Works:
When you are nearing the next milestone corresponding to the draw schedule (eg. the lock up stage), you will request an inspection. The inspector works with the lender and will verify that the work is complete. They often visit the site as well.
As your project progresses, the draw amount is computed based on the percentage completed. This amount is then sent to your lawyer, who subsequently pays your builder on your behalf (after withholding the necessary builder’s lien holdback as required by law).
The formula used to calculate the maximum draw advance is as follows:
Max Draw Amount ($) = (% Complete) * (Total Project Cost) – (Down Payment) – (Total Draws Already Made)
You’ll notice that the formula is not actually related to the actual cost to get to the next stage. It’s instead driven by the formula!
This is one of the biggest misconceptions around construction financing and can cause liquidity challenges so you need to pay attention to the net cash required between draws!
The completion mortgage is related to the builder / developer keeping the property after construction.
If you are working directly with an A lender or B lender, they often will loop the completion mortgage into the initial review. This will smooth out the processing of the mortgage and financing game plan. The completion mortgage in this case is a standard mortgage. The qualification, rates, loan to value and costs are the same as normal residential lending.
If you are doing the construction financing with a private lender and you intend to keep the property, you likely will want to “exit” into a better long term mortgage product. This typically would be a refinance at the end of the project and you would look at standard A or B lender financing. This will require qualifying for the mortgage so it’s best practice to get pre-qualified for this before taking on the project at all.
Of course, if you intend to sell the property, this phase is not as relevant. I do suggest reviewing it just in case for a potential exit plan.
One risk when building to sell is a soft market. This may cause a delay in the sale, or at worst, no buying activity for that product at all!
George and Rebecca want to buy some land and build a house on it. The land they’ve found has a value of $500,000 and they will need to get mortgage financing on it.
Currently, the land is already serviced and re-zoned.
They get some estimates from builders and determine that their project will cost $500,000 to complete. The major milestones align with a 4 draw construction mortgage. The lender in this case is really loose with their Loan to Cost ratio and will go all the way up to 75% LTC.
<to fill in>
% Complete – the estimate of the percent value for each milestone in the draw schedule
Total Advance to Date – this is the total amount of funds that the lender has given to George and Rebecca at the start of that phase. It’s effectively the mortgage loan size disbursed
Remaining Construction – the percent value of the remining construction project
Cost to Complete Construction – the estimated remaining cost given how much construction project is still waiting to be completed
Lien Holdback Required – Lenders generally require a lien holdback (I will create a separate post about this shortly)
Available Advance Amount – this is how much funds will be made available at the end of that phase. It is the amount of capital the lender will disburse from the total draw mortgage
Cost to get to next draw – The total amount of cash required for the construction during that phase
Net Cash Position before next draw – this is how much cash is required (construction cost plus potential down payment) before the next draw is disbursed
One the biggest challenges with construction financing is the amount of capital and liquidity a builder or developer needs.
In standard residential financing, you can buy a property with an 80% mortgage and only need 20% down payment. It’s also straight forward financing with no draws.
It’s completely different in the construction financing space.
Because of the non-intuitive construction draws, the land draw, and the lower loan-to-value/loan-to-cost with construction financing, you will actually need quite a bit of capital to get the deal done.
One of the decision factors in which lender to use is how many draw schedules and what LTV/LTC they allow.
From George and Rebecca’s example above, you will notice on the far right hand side there is the column “Net Cash Position Before Next Draw”.
This is the cash required at each phase.
To understand how much cash you will likely need, you find the largest negative net cash position in that column. In their case it’s the second row with $395,000.
This means that for George and Rebecca (example from the case study) to take on this project they will need at least $395,000. (Note: this is not inclusive of fees, interest, delays, or overages).
Most construction loans are interest only loans, meaning there is no principal pay down – which makes sense because you need the funds to build!
There’s typically 3 ways the interest is paid:
Many lenders may also require additional cash reserves to cover unforeseen costs, or even cash reserves to pay for the interest associated with the mortgage.
When looking at construction financing, there can be several different options to finance. Each with their own pros and cons.
MAJOR thing to keep in mind with these notes, credit markets change drastically all the time. Some features may exist during times of loose monetary and credit cycles where as many features and lenders may pause lending construction loans when credit tightens.
Pros
Cons
A Lenders
Best rates, fees and terms (aka much cheaper than private lending)
Seamless transition into the completion mortgage
Typically fund based on the borrower as opposed to the property so can be easier in smaller areas
Restrictive on where the capital comes from
You need to qualify with standard mortgage guidelines. Can be difficult to income qualify
Typically will have lower loan-to-value / loan-to-cost which means you may need to bring extra cash into the build
May require a licensed or registered builder – so may not be a great option for self builds
Limitations on number of properties, number of mortgages, use of property
B Lenders
Private Lenders
More flexible in their loan-to-value/loan-to-cost calculation and draw schedules
More flexible with their payment options – some can even do balloon payments
Many don’t require income qualification or debt servicing qualification
Don’t have a limit on number of doors or projects on the go
More expensive. Rates and Fees involved can be steep
If you intend to hold the property after you will have to refinance into the completion mortgage
Now, this can all seem like a lot. And it is.
That’s why I’ve built a construction financing and draw schedule worksheet!
Before I put the link, please remember that every lender is different AND you still have to qualify. This worksheet is intended to give you a feel for how construction financing works and for the liquidity / cash requirements.